Solar CAPEX and OPEX Explained
Evaluating a solar investment requires looking beyond the headline "per-watt" installation quote. Both upfront Capital Expenditure (CAPEX) and ongoing Operating Expenditure (OPEX) over the 25-year asset life determine real project viability.
1. Solar Project CAPEX Breakdown
Typical turnkey EPC CAPEX for a commercial or industrial rooftop solar project includes:
- PV Modules (40% – 50%): The largest cost driver; pricing varies significantly between Domestic Content Requirement (DCR) modules and non-DCR imported/domestic N-type TOPCon or Mono-PERC panels.
- Inverters & Power Conditioning (10% – 15%): String or central inverters with monitoring hardware.
- Mounting Structure (10% – 15%): Hot-dip galvanized (HDG), Galvalume, or anodized aluminum structures engineered for local wind loads.
- Balance of System (BoS) (10% – 15%): DC/AC cables, ACDB/DCDB, earthing pits (IS 3043), lightning arresters, and walkways.
- Engineering, Installation, Liaison & Net Metering (10% – 15%): Civil waterproofing, labor, CEIG/DISCOM approvals, bi-directional meters, and contingencies.
2. Solar Project OPEX Breakdown
Solar plants have low running costs, but they are never zero. A bankable financial model must budget for:
- Routine O&M & Module Cleaning: Annual AMC fees (often ₹500 to ₹1,000+ per kWp/year depending on scale and frequency), escalating at 4–5% annually.
- Insurance: Standard Fire & Special Perils / Machinery Breakdown coverage.
- Inverter Replacement Reserve: String inverters typically have a 10–12 year operational life; budgeting a Year 11–13 replacement reserve prevents surprise cash outflows.
NEED PROJECT-SPECIFIC ANALYSIS?
Apply this engineering framework directly to your facility or tender.
Technical & Professional Disclaimer
Indicative component shares vary with project size, module technology (DCR vs. non-DCR), roof complexity, and market commodity prices.